A group practice commissioned a local building company to build their own medical centre comprising 370 m2 (4000 ft2) of building with an adequate car park at a total cost of 60 000 pounds with design to completion in nine months. A bank loan for 10 years was assigned to the partnership and each partner made his own arrangements for repayment. The updated cost for June 1979 is 80 000-85 000 pounds. Building a centre in this way is professionally and financially rewarding.